The Project milestones, as per Schedule-G of Concession Agreement are as follows:
SUMMARY OF HIGHWAY PROGRESS
| Sl. No. |
Description of Item |
Unit |
Scope |
Total Scope |
| LHS |
RHS |
| 1 |
Sub-Grade |
Km. |
48.02 |
48.02 |
96.04 |
| 2 |
CTSB |
Km. |
48.02 |
48.02 |
96.04 |
| 3 |
WMM |
Km. |
48.02 |
48.02 |
96.04 |
| 4 |
DBM |
Km. |
48.02 |
48.02 |
96.04 |
| 5 |
BC |
Km. |
48.02 |
48.02 |
96.04 |
| 6 |
RE-Facia Erection |
Sqm |
36529 |
36529 |
73058 |
| 7 |
Road Side Drain |
Km. |
13.29 |
13.29 |
26.58 |
| 8 |
Slip Road / Service Road |
Km. |
15.42 |
15.42 |
30.84 |